Three Possible Scenarios How To Perform This Important Task.

Once when your Focused build project is ready for  Go-Live you have to hypercare/maintain what have you delivered in your last release.

There re 3 scenarios how to perform this very  important task:

  1. R2D Simple (4 Systems Landscape) : .once your current release is in hypercare  you next release will take over unfinished change documents and  support old release utilizing preliminary import (does not follow release phases) approach inside new release. Continuous innovation plus bug fixing with preliminary import.

  2. R2D Extended (4 Systems Landscape) : After successful Go-Live  you can move your corresponding  cycle (S1MR)  to the Hypercare , therefore your current release cycle will become visible to the newly created FB Maintenance project and you will keep you current cycle in hypercare until you finishes support of your current Go-Live release. The next release will take over unfinished change documents but fixes will stay in the separate Maintenance project related and sticked with old cycle.

  3. SM Full Scope (6 Systems Landscape): use CHARM for the maintenance of your current landscape/release . This approach is valid in case a customer already have  CHARM implemented  and customer decided to with the new implementation utilizing  Focused Build tools.

This blog will explain Scenario 2  (R2D Extended (4 Systems Landscape) which means  4 systems landscape and only use of Development branch. Maintenance branch is not configured.

Branch Concept Overview



ree

The above picture represented in the Solution Manager should look like is presented in the below branch concept. As is presented in the below picture we are dealing just with 4 systems and utilizing just development branch.

The PPM and Release Planning Interaction

How this Maintenance scenario #2 will work once you include PPM projects and Releases  the best explanation is in the  below screenshot.

ree

Lets start with the preparation of your Solution Manager FB part.

Prerequisites steps.

  1. The proof of concept environment is Solution Manager  7.2 SP7 ST-OST SP2. Question : Is this possible in the  ST-OST SP1 ? you have to check OSS notes -Out of the box ST-OST SP1 will not underpin this possibility.

  2. We assume you went trough the Focused Build Configuration guide (link)  and followed instructions to  adjusted yours FB completely .


Practical Part : Additional Configuration of the FB to use Maintenance Project

The Preparation of Solution Administration

Branch concept should be organized in the way that your all system except productions should be part of the  Development branch (DEV,QAS and PPRD) and your PRD systems is going to be part if Productive branch.