S1IT Maintenance Work Package – Focused Build SP2 Scenario R2D Extended (2)

Prerequisite check

-PPM project crosscheck

On the PPM level you should check is your Maintenance project correctly created. In this action you should check following things:

  1. Project wave is in status Released

  2. Sprint  in the selected Wave is released as well.

In the FIORI App Project Management select project you created recently.



ree

Go to the Wave and check is your wave in status released.

  1. Select proper wave of our project

  2. Check current status is your status Released

  3. If your status is not Released you should select this status from the drop down menu selected under step 3.

  4. In order to perform any changes you have to put project in the Edit mode by clicking on the pen icon.


....more information you can find on the link